Saudi Arabia Renewable Energy Target: 50% by 2030
Saudi Arabia’s renewable energy target is to source 50 percent of electricity from renewables by 2030, implying roughly 130 GW of installed solar, wind, and storage capacity against a 2018 baseline of effectively zero. By the close of 2025, operational renewable capacity had reached approximately 13 GW, with a contracted pipeline of more than 40 GW progressing through engineering, procurement, financial close, or construction. The build-out is being delivered through the National Renewable Energy Program (NREP), executed by the Renewable Energy Project Development Office (REPDO) and the Saudi Power Procurement Company (SPPC), with a tariff trajectory that has repeatedly set global records since 2021.
This entry catalogs the current state of the programme, the role of PIF and its flagship developer ACWA Power, the project pipeline through 2030, the parallel build-out of battery storage and domestic manufacturing, and the structural risks that explain why several independent analyses still project a 2030 outturn closer to 75 GW than the headline 130 GW.
NREP and the 2030 Capacity Target
The National Renewable Energy Program, launched in 2017 under the Ministry of Energy, is the policy spine of the Saudi renewables build-out. Its two delivery tracks complement one another: a competitive procurement track run by SPPC, in which independent power producers (IPPs) bid for 25-year power purchase agreements; and a strategic track in which PIF directly negotiates project allocations with ACWA Power, Aramco subsidiary SAPCO, and PIF-owned developer Badeel. Together these tracks aim to deliver the 130 GW target laid out in Vision 2030, comprising approximately 58.7 GW of solar photovoltaic, 40 GW of wind, and the balance from concentrated solar power, waste-to-energy, and battery storage.
The Energy Minister has reiterated the 130 GW headline through 2025 and into 2026, but the achievable figure depends on annual procurement volumes that have only recently begun to scale. Saudi Arabia would need to install over 23 GW per year between 2026 and 2030 to close the gap; actual completions in 2024 and 2025 ran in the low single-digit gigawatt range. GlobalData and other independent forecasters now model a 2030 outturn of roughly 74 GW, implying that the 50-percent generation share will likely slip into the early 2030s even if the procurement pace accelerates further. The political commitment, however, has not been diluted: each successive NREP round has been larger than the last, and parallel manufacturing and storage tenders are now sized to absorb that pipeline.
REPDO and the Auction Cadence
REPDO, housed within the Ministry of Energy, designs the technical and commercial structure of NREP tenders. SPPC acts as the offtaker, signing 25-year (and in some recent projects 35-year) PPAs. The bidding architecture has consistently produced tariffs at or near global lows because it combines exceptional resource quality (DNI of 2,200-2,500 kWh/m^2/year in central and northern provinces), low-cost land, sovereign-backed offtake, and aggressive participation from Chinese and Gulf-based EPC contractors.
By the end of Round 6 in October 2025, the cumulative awarded capacity through NREP exceeded 18 GW across solar PV and wind, with several rounds running concurrently as projects move through preferred-bidder, financial close, and construction phases.
PIF and ACWA Power: The Strategic Track
PIF is both the policy architect and the dominant equity provider behind Saudi renewables. In April 2025, PIF announced a SAR 31 billion (approximately USD 8.3 billion) commitment with ACWA Power, Badeel, and SAPCO to develop 15,000 MW of additional renewable capacity, reinforcing the strategic-allocation track that runs alongside competitive auctions. The arrangement leverages ACWA Power’s developer expertise, Badeel’s PIF mandate, and SAPCO’s link to Aramco’s industrial demand.
ACWA Power is the listed pure-play that translates this allocation into investable equity. Listed on the Tadawul under ticker 2082 since October 2021, ACWA Power completed a SAR 7.1 billion (approximately USD 1.9 billion) rights issue in 2024, with PIF (44.16 percent) and Vision Invest (22.75 percent) subscribing in full. The capital raise was earmarked to fund equity contributions across the Saudi pipeline, the NEOM green hydrogen complex, and select international projects. As of 2026, ACWA Power’s managed portfolio across power, water, and green hydrogen exceeds USD 100 billion, with Saudi Arabia accounting for the largest share by project value.
PIF’s other vehicles in the renewables stack include the Renewable Energy Localization Company (RELC), which holds equity in domestic solar manufacturing joint ventures, and Vision Industries, which co-invests across the manufacturing chain. The combined effect is that PIF can both pull demand (via NREP procurement and direct allocations) and push supply (via factories on Saudi soil), accelerating learning-curve gains that further compress tariffs.
Project Pipeline: Utility Solar
Operational Anchor Projects
The 1.5 GW Sudair Solar PV plant in Riyadh province was the first project under the strategic-allocation track and remains one of the world’s largest single-site solar facilities. Developed by an ACWA Power-led consortium with PIF and Aramco, Sudair achieved commercial operation in 2023 at a tariff of USD 12.39/MWh (1.239 cents/kWh), which at the time was the second-lowest globally. The plant supplies approximately 184,000 homes equivalent and avoids around 2.9 million tonnes of CO2 per year.
The 300 MW Sakaka PV plant in Al Jouf, awarded in NREP Round 1 to a consortium led by ACWA Power and commissioned in 2019, was the first large utility-scale solar project in the Kingdom and originally bid at USD 23.40/MWh. Although now eclipsed on price, Sakaka provided the operational data that gave international lenders comfort with the Saudi PPA framework.
Al Shuaibah and Ar Rass: The 2025-2026 Wave
The Al Shuaibah complex in Makkah Province moved into operation through 2025. Al Shuaibah 1 (600 MW) and Al Shuaibah 2 (2,031 MW) reached financial close in August 2023 at a combined investment of approximately USD 2.37 billion, developed by ACWA Power, Badeel, and SAPCO. Al Shuaibah 2 set a global low at USD 10.40/MWh (1.04 cents/kWh) at award. The project completed phased commissioning across 2025 and represented one of the largest single-site solar generation assets globally upon full operation.
The 2 GW Ar Rass II Solar PV IPP in Qassim is being developed by ACWA Power under a 35-year PPA with SPPC and is one of the projects supporting the SAR 31 billion 2025 PIF allocation. Ar Rass II is paired with the smaller Ar Rass I (700 MW) project from Round 4. Both feed into the central transmission grid via the SEC’s expanding 380 kV backbone.
NREP Rounds 4 through 7
Round 4 (awarded in 2023) delivered approximately 3.3 GW across six projects and saw the entry of TotalEnergies, EDF, Marubeni, and Korea Electric Power Corporation (KEPCO) alongside ACWA Power consortia. Round 5, awarded in 2024-2025, allocated 3.7 GW across four solar projects: the 2 GW Al Sadawi plant in the Eastern Province (Masdar/KEPCO consortium at USD 12.90/MWh), the 1 GW Al Masa’a project in Hail (USD 12.94/MWh), the 400 MW Al Henakiyah 2, and the 300 MW Rabigh 2.
Round 6, awarded in October 2025, added approximately 3 GW across four solar projects, including the 1.4 GW Najran solar plant developed by Masdar at USD 11.00/MWh, the second-lowest LCOE for solar globally on record at that date. Round 7, launched in late 2025 and progressing through 2026, totals 5.3 GW comprising 3.1 GW of solar across four sites and 2.2 GW of wind across two sites, including the previously announced Yanbu and Al Ghat allocations.
Project Pipeline: Wind
Wind has historically lagged solar in Saudi Arabia because the resource is less ubiquitous, but the Kingdom has identified high-quality sites along the Red Sea coast, in the northwestern desert, and in the central plateau capable of supporting more than 20 GW.
The 400 MW Dumat Al Jandal wind farm in Al Jouf was the first utility-scale wind project, owned by Masdar and EDF Renewables, fully operational since December 2021 with 99 Vestas V150-4.2 MW turbines. It supplies approximately 70,000 households and avoids about 1 million tonnes of CO2 annually.
The next-generation pipeline includes the 700 MW Yanbu wind farm in Madinah province, for which SPPC signed the PPA on 12 July 2025 with a Marubeni-Ajlan & Bros consortium at total investment of approximately USD 458 million; the 600 MW Al Ghat wind IPP, awarded at a record-low USD 15.66/MWh and the lowest wind tariff globally at the time of award; and the 500 MW Waad Al Shamal wind farm in the Northern Borders Province, also developed by Marubeni and Ajlan & Bros. Together these projects raise the operational and contracted Saudi wind fleet above 2.2 GW and demonstrate that wind tariffs in the Kingdom can compete with solar plus four-hour storage at the LCOE level.
Battery Storage and Solar Manufacturing
BESS: From Pilot to Industrial Scale
Battery energy storage shifted from pilot to industrial scale during 2025. In December 2025, a 2 GW / 7.8 GWh standalone battery storage system jointly delivered by Sungrow and Algihaz was synchronised with the Saudi grid, ranking as one of the largest single battery deployments globally and providing four-hour duration capacity to support solar integration during evening peaks.
In parallel, SPPC launched the Kingdom’s first formal BESS tender in November 2024 for 2 GW / 8 GWh of battery storage across four sites: Al-Muwyah and Haden in Makkah, Al-Khushaybi in Qassim, and Al-Kahafa in Hail. Each site is sized at 500 MW with four-hour duration, totalling 2,000 MWh of energy capacity. Pre-qualification announced in January 2025 yielded 33 bidders including Masdar, ACWA Power, EDF, TotalEnergies, and Jinko Power. Awards are structured as 15-year build-own-operate storage service agreements with SPPC. Saudi Arabia’s broader pipeline runs to approximately 30 GWh of contracted or pre-tender BESS capacity, against a 2030 target of 48 GWh.
Domestic Solar Manufacturing
The Kingdom is industrialising the supply chain alongside the deployment programme. PIF, through RELC and Vision Industries, has signed joint ventures with Chinese manufacturers covering ingot-to-module capacity of approximately 30 GW per year. The flagship JinkoSolar venture is a 10 GW n-type solar cell and module factory in approximately USD 1 billion of investment, with RELC and JinkoSolar each holding 40 percent and Vision Industries 20 percent; the plant is targeting commissioning in early 2026. A separate TCL Zhonghuan venture covers a 20 GW ingot-and-wafer plant at approximately USD 2.08 billion. Sungrow, Trina Solar, and several inverter and BESS integrators have additional Saudi facilities at various planning stages.
The strategic intent is to convert the demand certainty embedded in NREP procurement into permanent industrial capacity, capturing assembly value, training a domestic workforce, and supplying both Saudi and regional projects (Egypt, Iraq, the Levant, North Africa) from a tariff-advantaged base inside the GCC customs union.
Hydrogen Integration
The Kingdom’s hydrogen strategy is anchored by the NEOM Green Hydrogen Company (NGHC), the equal joint venture between NEOM, ACWA Power, and Air Products. The complex, sometimes referred to as the Helios green hydrogen project, integrates approximately 4 GW of dedicated solar and onshore wind capacity feeding 2.2 GW of thyssenkrupp electrolysers, with output converted to green ammonia via Air Products’ technology. Financial close was achieved in May 2023 at a total investment value of USD 8.4 billion. By the start of Q1 2025, NGHC reported approximately 80 percent overall construction completion, with the renewable generation set to be commissioned by mid-2026 and first ammonia output expected in 2027. At full ramp the plant will produce around 600 tonnes of hydrogen per day and up to 1.2 million tonnes of green ammonia per year, abating approximately 5 million tonnes of CO2 per year on a lifecycle basis.
NGHC is significant for the renewables sector because it is the first project in Saudi Arabia where renewable generation is a feedstock rather than a grid commodity. The PPA structure is internal to the JV; the offtake risk is on the green ammonia market, which has matured through 2024-2026 with European Hydrogen Bank auctions, Korean and Japanese tenders, and bilateral term sheets with end-users in steel, fertilisers, and shipping.
Beyond NEOM, hydrogen-ready feasibility work is advancing at Yanbu, Jubail, and the Red Sea Project, with Aramco, SABIC, and Ma’aden each evaluating either captive renewable generation or PPAs from NREP-allocated projects to decarbonise existing operations.
Recent Developments 2024-2026
The cadence of announcements through this period illustrates the pace of the build-out:
- October 2024: Round 5 (3.7 GW) attracted a record-low solar bid of USD 12.90/MWh from Masdar/KEPCO for the 2 GW Al Sadawi project.
- November 2024: SPPC launched the world’s largest single battery storage tender at 2 GW / 8 GWh across four sites.
- June 2024: ACWA Power’s board recommended a SAR 7.125 billion rights issue, fully backstopped by PIF and Vision Invest.
- July 2024-mid 2025: PIF concluded JinkoSolar and TCL Zhonghuan manufacturing JVs totalling approximately 30 GW per year of cell-and-module and wafer capacity.
- April 2025: PIF announced the SAR 31 billion (USD 8.3 billion) ACWA Power-Badeel-SAPCO 15 GW renewable allocation.
- July 2025: Yanbu 700 MW wind PPA signed with Marubeni-Ajlan consortium.
- September 2025: Round 7 launched at 5.3 GW (3.1 GW solar plus 2.2 GW wind).
- October 2025: Round 6 awarded 3 GW of solar including the 1.4 GW Najran project at USD 11.00/MWh.
- December 2025: Sungrow-Algihaz 2 GW / 7.8 GWh BESS synchronised to the Saudi grid.
- Q1 2026: NGHC at approximately 80 percent construction completion across all sites; JinkoSolar Saudi factory commissioning underway.
Risks and Challenges
The build-out faces structural and operational risks that explain why several independent forecasters model a 2030 capacity outturn well below 130 GW.
Pace of installation. The mathematical gap between actual delivery (low-single-digit GW per year) and the required runrate (over 23 GW per year) is the single largest risk. EPC capacity, transmission interconnection queues, and substation upgrades have all been bottlenecks despite low project-level capex.
Grid integration and curtailment. The SEC and the Electricity & Cogeneration Regulatory Authority must build out 380 kV and 500 kV backbone capacity in parallel with generation. Without it, daytime solar curtailment will rise as penetration crosses 30 percent of generation. The 8 GWh BESS tender is an early structural response, but storage deployment must also accelerate to 5-8 GWh per year by 2027-2028.
Tariff sustainability. Bids in the USD 10-13/MWh range are below most international solar PPAs and only narrowly cover financing costs at scale. If interest rates remain elevated, lender returns compress and equity sponsors may demand pipeline allocation rather than competitive bid wins, slowing the merit-order benefits of pure auctions.
Resource and operational issues. Sand and dust deposition can cut module yield by 10-25 percent without active cleaning; robotic dry-cleaning systems are now standard but add opex. Summer ambient temperatures above 45 degrees Celsius reduce inverter and battery efficiency and accelerate degradation.
Domestic demand growth. Saudi electricity demand grew at approximately 4-6 percent per year through 2025 driven by air conditioning, water desalination, and industrial expansion (NEOM, Qiddiya, Diriyah, Red Sea, Riyadh metro, AI data centres). Even if 130 GW of renewables were online by 2030, residual gas-fired generation would remain meaningful unless storage and demand-side response scale in parallel.
Geopolitics and supply chain. Heavy reliance on Chinese cells, modules, wafers, and inverters exposes the programme to trade and tariff dynamics outside the Kingdom’s control. Domestic manufacturing JVs are the response, but they require Saudi cell production to come online before any meaningful import substitution begins.
Financing scale. The aggregate capex requirement to reach the 130 GW target, including grid and storage, is on the order of USD 200 billion through 2030. PIF, ACWA Power, international IPP sponsors, and Saudi banks supply the equity and debt, but the share of foreign capital depends on FX stability, tariff sustainability, and arbitration framework integrity.
Outlook to 2030
The renewables programme is now a load-bearing pillar of Vision 2030, the Saudi Green Initiative, and the broader energy transition strategy. The most plausible 2030 outturn, based on contracted pipeline plus realistic procurement velocity, is in the range of 75-95 GW of operational renewables, with battery storage of approximately 25-35 GWh and 4 GW of wind. That would deliver roughly 30-40 percent of generation from non-hydrocarbon sources by 2030, with the residual 50-percent target slipping into 2032-2034.
The economic logic for the Kingdom remains compelling regardless of the precise year of target attainment: each GWh of solar generation displaces approximately 1.7 barrels of crude or equivalent gas, freeing hydrocarbons for higher-value export or petrochemical conversion. At 2025-2026 marker prices, the 130 GW programme implies a structural reallocation of approximately 1 million barrels per day of hydrocarbon equivalent from domestic burn to export or downstream value capture by the early 2030s, with the corresponding fiscal upside flowing to the Saudi government.
The investment case for renewable energy capacity in Saudi Arabia therefore rests on three pillars: tariff compression that has already produced four global low records since 2021; a sovereign-backed offtake mechanism that gives lenders and IPPs unusual contract security; and an industrial localisation strategy that converts deployment volume into permanent manufacturing capacity. The risks are real but bounded by the same fiscal and political will that has carried the programme from a single 300 MW project at Sakaka in 2018 to more than 18 GW of awarded NREP contracts and a 2 GW BESS pipeline by the close of 2025.
For investors and analysts tracking the sector, the most consequential data points to watch through 2026-2027 are NREP Round 7 awards, the BESS Round 1 award and pricing, the JinkoSolar Saudi plant ramp, the NEOM Green Hydrogen Company commissioning, and the SEC’s transmission capex disclosures. Each provides a near-real-time gauge of whether the gap between Saudi Arabia’s headline 130 GW target and the realistic 75-95 GW outturn is closing or widening.
See our How to Invest in Renewable Energy, ACWA Power, NREP, REPDO, and Saudi Green Initiative entries for deeper coverage. External sources: REPDO, ACWA Power Investor Relations, IEA Saudi Arabia, Reuters energy desk, and MEED.
