Last verified: 1 September 2026. The Saudi Contractors Authority’s SCAVO series recorded 97 projects awarded from January through July 2026, with a combined value of SAR111.308 billion. That is the number to watch more closely than the multi-trillion-riyal universe of projects announced, displayed or proposed under Saudi Arabia’s development plans. It is also a number that needs a warning label. [S1]
The July report is a project-intelligence product, not a published government-procurement register. It analyses projects added to SCAVO, a platform operated through a partnership between the Authority and Onsite Ventures. Its disclaimer makes no guarantee of completeness, accuracy or reliability, and the public document does not list all 97 awards. [S1]
The defensible claim is therefore precise: SCA/SCAVO recorded 97 awards worth SAR111.31 billion through July. The data are a valuable leading indicator of execution. They are not yet a complete, independently auditable census of every Saudi contract.
| 2026 month | Recorded projects | Value (SARbn) | Share of seven-month value |
|---|---|---|---|
| January | 5 | 11.738 | 10.5% |
| February | 4 | 2.810 | 2.5% |
| March | 11 | 15.664 | 14.1% |
| April | 23 | 11.805 | 10.6% |
| May | 18 | 30.038 | 27.0% |
| June | 25 | 29.501 | 26.5% |
| July | 11 | 9.754 | 8.8% |
| Total | 97 | 111.308 | 100% |
May and June supplied SAR59.539 billion, or 53.5 per cent of the seven-month value. July then fell to SAR9.754 billion, 67 per cent below May by value. Award flow is lumpy; multiplying one strong month by twelve would manufacture a false annual pipeline.
July exposed the difference between a forecast and an award
The June report expected 23 projects to be awarded in July, more than 60 per cent of them in building and construction. The eventual July report recorded 11. [S2]
That was a shortfall of 12 projects, or 52.2 per cent, against the prior count forecast. It does not establish that 12 projects were cancelled. They may have slipped, been consolidated, fallen outside the extraction window or failed SCAVO’s recording process. It does establish why forecast awards cannot be booked as delivered procurement.
The same discipline applies earlier in the project cycle. The Authority’s 2025 annual report says the Future Projects Forum displayed more than 20,000 development projects worth over SAR3 trillion. [S3] That describes an opportunity universe. The SAR111.31 billion series describes projects recorded as awarded. Neither figure is construction revenue, cash expenditure, percentage complete or operating capacity.
An evidence-led project ledger should classify at least six stages:
- Policy target or masterplan — ambition without a procurement event.
- Project announcement — scope and estimated capex may still change.
- Tender or expected award — competition is open or anticipated.
- Award or signed contract — a contractor and commercial commitment exist.
- Notice to proceed and construction — mobilisation and physical execution have begun.
- Completion and operation — the asset is available for use and generating service output.
The July report moves 11 projects to stage four in SCAVO’s taxonomy. It does not move them to stage six.
The July award book was concentrated
Building and construction accounted for seven July projects worth SAR6.585 billion, 67.5 per cent of value. Infrastructure represented three worth SAR2.794 billion, or 28.6 per cent. One water-and-energy project contributed SAR375 million. [S1]
Geography was more concentrated still. Riyadh held seven projects worth SAR7.504 billion—76.9 per cent of July’s value. Hail had three worth SAR1.875 billion; the Eastern Province had one worth SAR375 million.
The five owner groups shown in the report accounted for ten projects and SAR7.616 billion, 78.1 per cent of value. The Royal Commission for Riyadh City led with three projects worth SAR2.794 billion. Cluster2 had three worth SAR1.875 billion. A Diriyah Gate Development Authority/PIF grouping had two worth SAR1.163 billion; Midad Real Estate Investment and Development had one worth SAR1.035 billion; and Qiddiya Investment Company had one worth SAR750 million. [S1]
The named-project page includes the first phase of a Diriyah road and Four Seasons hotel-and-residences package; phase three of Riyadh’s Al Thumamah road development; expansion of Hail airport’s new southern terminal; an equine hospital at Qiddiya; and the Vida residential project. [S1]
These are more useful than a masterplan value because they attach owner, sector and region to an award-stage event. Yet the public page omits contractor names, award dates, contract types, commencement dates and precise contract values for each named project. It therefore cannot answer how much of July was genuinely new work, re-awarded scope or a variation to an existing package.
The delivery wave runs into 2030
The Authority allocated all July projects to three expected completion years:
| Expected completion | Projects | Recorded value (SARbn) | Share of July value |
|---|---|---|---|
| 2028 | 3 | 2.794 | 28.6% |
| 2029 | 5 | 5.441 | 55.8% |
| 2030 | 3 | 1.519 | 15.6% |
More than half of July value is scheduled for 2029 completion. That creates a plausible demand window for labour, materials, equipment, subcontractors, insurance and working capital through 2027–29. It is not a spending schedule. Contract value may include design, equipment and risk allowances; payments follow milestones; and delay can shift activity across years.
The cost backdrop also matters. GASTAT’s Construction Cost Index was 2.3 per cent higher in July than a year earlier and flat month on month. [S4] Stable monthly input costs help tender certainty, but a nominal award total does not show the physical volume purchased. Analysts need to deflate values, separate buildings from civil works, and track variations.
Nor should the cumulative value be treated as 2026 construction demand. A SAR1 billion award made in July can generate mobilisation in 2026, structural work in 2027, systems installation in 2028 and retention payments later. Imported equipment may absorb part of the contract without a matching increase in domestic construction output. Advance payments can precede physical progress; contractor revenue recognition can differ from owner cash payments.
The useful forecast is therefore not SAR111.31 billion divided by the remaining months to completion. It is a package-level expenditure curve. Each award needs a start date, duration, expected monthly progress and imported-content assumption. Summed across projects, that curve would show when demand peaks for cement, steel, mechanical systems, cranes, engineers and skilled trades. The July completion table points to pressure through 2029, but cannot size it.
This distinction also protects comparisons. Total project capex can include land, finance, design, technology, operating equipment and pre-opening costs outside the contractor’s award. If SCAVO records contract value for one project and total capex for another, aggregation creates a category error. The public report does not publish a field definition sufficient to rule that out.
Countercase: awards can still overstate execution
A signed award is a much stronger signal than an announcement, but it is not immune to failure. Scope can be reduced, contractors replaced, notices to proceed delayed and completion dates moved. An EPC award may cover an entire package; a construction-management appointment may not. Comparing both as identical “project value” creates false precision.
The SCA report itself gives the countercase. Its introduction refers to projects “offered” in July and projects added to SCAVO, while its charts call them awarded. The document’s disclaimer rejects guarantees about completeness and reliability. Those textual tensions do not invalidate the data; they require the series to be audited against owner and contractor disclosures.
A robust public tracker would publish one row per award with:
- project, package, owner and contractor legal names;
- award and signature dates, notice-to-proceed status and original completion date;
- contract value, currency, VAT treatment and whether the number is contract value or total project capex;
- procurement form and the share attributable to construction;
- previous award, rescope or variation identifiers;
- monthly progress, certified payments, revised value and revised completion date.
Without that ledger, the 97-project count cannot be checked for duplicate packages or later amendments, and PIF-, Aramco- and NHC-related exposure cannot be calculated reliably for the full period.
What would falsify the execution signal
The award-led thesis would weaken if awarded packages fail to receive notices to proceed, if owner or contractor disclosures show material cancellations, if certified payments lag for several quarters, or if the 2028–30 completion distribution shifts repeatedly to the right. It would strengthen if mobilisation is visible, contractor backlogs reconcile to the SCAVO values and physical-progress data track the reported completion years.
July’s miss against its own forecast is not evidence that Saudi construction stopped. It is evidence that the market should price delivery stages separately. SAR3 trillion of forum opportunities is a horizon. SAR111.31 billion of recorded awards is a narrower commitment. The next proof is work performed—and the final proof is an operating asset.
Related Vision 2030 Context
- Saudi industrial occupancy above 90% points to a shortage of suitable space
- Saudi government tenders reported SAR63 billion of local-content value
- Diriyah’s SAR2 billion residences financing is a facility, not delivered construction
Sources
- [S1] Saudi Contractors Authority, Contracting Sector Overview Report: July 2026, SCAVO data extracted 4 August 2026; exact monthly, sector, region, owner, completion-year and selected-project tables. public PDF copy
- [S2] Saudi Contractors Authority, June 2026 report announcement, including the forecast of 23 July awards; corroborated by the Saudi Press Agency. SCA; SPA
- [S3] Saudi Contractors Authority, 2025 annual report: Future Projects Forum displayed more than 20,000 projects worth over SAR3 trillion. interactive annual report
- [S4] General Authority for Statistics, Construction Cost Index, July 2026: headline index up 2.3% year on year and unchanged month on month. GASTAT publication listing
